5/5/16
Today we set up this blog.
5/10/16
Today I learned how to solder and had the interview.
5/12/16
Today I soldered a bit of the control box but I did not finish. I did finish Strip the power cord and putting on the alligator tips. I plan to finish by next class.
5/13/16
Today I finished the control box but during testing it did not pass for one of the switches was not working. Mrs. S gave our group an old control box after trying to fix the box.
5/16/16
Today we finished mounting the motors and were able to test our ROV in the water it seems as everything is going well and that we have a working ROV. I believe that we are plan to work on the making adjustments to do the challenges and focus on operation Fix it.
5/20/16
Today we tried to to work on the operation fix it challenge with a coat hanger but it failed. We will have to try and find a better way to fix the problem.
5/24/16
Today we worked on operation fix it and managed to engineer a way to cap the valve. We made many fish hooks out of a hanger and fishing string. We able to cap the valve today due to these fish hooks it just takes a lot of work to control the ROV in a way to pick it up.